How Much Material Do I Need?

Cubic yards = length (ft) x width (ft) x depth (ft) / 27. Round up to the nearest half yard, add extra for compaction on base materials, and use the per-material weights below to estimate tons.

By the Earthstone Materials Team  ·  Last updated: September 26, 2026

The math is simple and it works for every material we sell: cubic yards = length (ft) x width (ft) x depth (ft) / 27. Measure the area in feet, convert depth from inches to feet by dividing by 12, multiply, then divide by 27. Round up to the nearest half yard. That is the whole formula.

Step-by-step

  1. Measure length and width of the area in feet.
  2. Pick a depth in inches: 3 to 4 inches for most top layers, 4 to 6 for base layers, 1 to 2 for mulch-like topsoil over beds.
  3. Divide the depth by 12 to get feet.
  4. Multiply length x width x depth-in-feet, then divide by 27.
  5. Round up to the nearest half yard, and add a compaction allowance for base materials.

How heavy is a cubic yard? (estimates)

Weight per cubic yard varies by material and moisture. These are standard industry approximations for estimating tons, not scale weights:

MaterialTons per cubic yard (approx)
Crushed stone (#57, #4, crusher run, drain rock)~1.5
Limerock base~1.5
Gravel~1.4
Asphalt millings~1.4
Sand~1.35
Fill dirt~1.3
Rip rap~1.3
Topsoil~1.1

Worked examples

ProjectSizeDepthCubic yards (approx)Tons (approx)
2-car driveway, #57 stone20 x 20 ft4 in~5~7.5
Driveway base, crusher run20 x 40 ft4 in~10~15
Garden beds, topsoil10 x 20 ft2 in~1.5~1.7
Raising grade, fill dirt30 x 30 ft6 in~17~22

Not sure which material your project needs? Take the material selector quiz first. Then skip the mental math and use our material calculator: pick a material, enter your measurements, and it gives cubic yards, estimated tons, and estimated truckloads, then pre-fills your quote.

Frequently asked questions

A typical tri-axle dump truck hauls about 12 cubic yards, which is the standard full load for most aggregate deliveries. Smaller single-axle trucks carry less. Our calculator estimates your loads at about 12 yards each.
Multiply cubic yards by the material's weight per yard. As a rule of thumb, crushed stone weighs about 1.5 tons per yard, gravel about 1.4, and topsoil about 1.1. These are industry approximations, and moisture can change them.
Yes for base materials. Crusher run, FDOT limerock base, and recycled concrete base rock lose 10 to 20 percent of their volume when compacted, so order accordingly. Stone that stays loose, like #57, does not compact, but uneven ground still eats some yardage.
Three to four inches is the standard finished layer over a compacted base. The base itself is often another 4 to 6 inches. Soft or low ground may need more base, not just a thicker top. For driveway-specific math, see our how much gravel for a driveway guide.
We deliver a minimum of 4 cubic yards per load. Pricing depends on the material and your drop-off ZIP code, and same-day delivery is available on in-stock materials.

Ready when you are.

Tell us the material, quantity, and drop location. We'll handle the rest.

Get a fast quoteCall now